1

CASE
STUDY
The strange case of Jacob’s Well, in which an ancient
building sheds a storey to preserve its history
To restore, so various editions of The
Oxford Dictionary tell us; means “to bring
back to the original form”. But with an old
building which has taken many forms dur-
ing its long life, it can be very hard some-
times to judge exactly what this implies.
Jacob’s Well, one of the most important
15th century houses in York, is just such a
building.
Jacob’s Well officially opened to the
public last Autumn after nearly a decade of
closure, having been brought back, quite
literally, from the brink of collapse, large-
ly thanks to the daring and dogged efforts
of Peter Marshall Architects and restora-
tion specialists, William Anelay Ltd of
York. Bringing this about, however, has
not been an easy task.
The fine, timber-framed building was
originally built to house the Chantry
priest of Holy Trinity Priory, Micklegate,
which continues to own and administer it
as a church hail. In the 18th and 19th cen-
turies, however, it did time as a pub trad-
ing under the name Jacob’s Well, and in
1815 a brick second storey was thrown up
on top of the original structure.
The original oak frame proved sturdy
enough to stand up to the weight of the
many tonnes of extra bricks which it had
never been meant to support, but by the
beginning of this century, when a minor
refurbishment was undertaken in conjunc-
tion with the restoration of Holy Trinity
Prior, the upper storey was visibly leaning
forward over Trinity Lane below. At the
same time, the floor of the first story was
bowing at the centre and sagging at the
sides, with the load from the additional
brick not actually being transferred to
ground level. It was simply resting on the
overhanging butts of the timbers compris-
ing the top of the old wooden frame and
was a full 9 inches out of plumb.
Under the direction of English Her-
itage, tests were undertaken to determine
whether or not the timber frame was still
subsiding under the stress of the added
JACOB’S WELL, YORK

brick. Pairs of small metal studs were sunk
into either side of several joints all around
the frame. The distance between the studs
in each pair was then measured monthly
over a period of nearly two years. In the
end it was found that at least the frame had
done all the sagging it was going to do and
would not suddenly collapse of its own
accord.
Still, action had to be taken, and two
possible courses were open. Either the
lower half of the building could be rein-
forced with so much structural steel work
that its original Tudor character would be
virtually lost, or the upper half could be
removed and replaced by a reconstruction
of the orginal Tudor roof. It seemed like a
straightforward choice renovation or
restoration.
However, the approval of 13 different
conservation and amenities bodies, in
addition to that of York City Council, was
required in order to go ahead with either
plan. Certainly, the Tudor bottom half of
the building was of great historic signifi-
cance, but were not the Georgian additions
also of Grade I listed status along with the
rest?
After almost three years of negotiation,
involving SPAB and The Georgian Group,
consent was obtained for the more radical
of the two options. The integrity of the
Tudor building would be restored at the
expense of the Georgian additions. Follow-
ing the award of a £15,000 grant from
English Heritage, The Jacob’s Well
Appeal was set up under the patronage of
the Archbishop of York to cover the
remaining costs amounting to roughly
£100,000.
As specialists in restoration who had
worked on numerous other important his-
toric buildings in and around York,
William Anelay Ltd were chosen to under-
take the work on grounds of both cost and
capability. After the Georgian roof and
second storey had been carefully removed
while supporting and protecting the
building with a veritable forest of scaffold-
ing, the oak frame’s more fragile joints and
beams were reinforced with thin steel
strapping, while also renewing the most
damage and decayed timbers.
By looking at the peg holes and joint
slots at the top of the frame, Anelay’s join-
ers, with help from the architects and
English Heritage, were able to reconstruct
the basic design of the 15th century roof.
It had been of ‘crown and post’ construc-
tion, gabled to the North, and pitched at
about 550; its successor would follow the
same plan.
The roof had to be built to match all the
anomalies of the frame beneath, which had
never been too square in the first place and
had now sagged and twisted under its
great weight of years and extra brick such
that it was a couple of feet wider and high-
er at one end than at the other.
Above:Jaeobs Well prier to restoration showing the 19th
century roof and upper storey looking somewhat cumbersome
atop the 15th century lower storeys.
10
CONTEXT 33

1